BID PACKAGE 10 - BID FINAL

General Overview:

The Bid Package includes construction of a new 70,000 SF Elementary School at the existing site of West Middle School.

Bidding Documents:

• Drawings

• Specifications

• Hard copy printing is responsibility of bidder

• Electronic documents available through Smart Bid Net to invited bidders

Instructions to Bidders:

Anticipated Out to Bid – January 11, 2019

Pre-Bid Date – To Be Determined

Anticipated Bid Date – February 7, 2019

Bid Proposal Form – Section 00 41 23 (include signed scope of work with bid form)

Bid Delivery – Please direct all bids to JE Dunn Construction (Molly Lyons)

Must be in sealed envelope; Can be emailed with the exception of the following scopes:

• Concrete

• Precast

• Masonry

• Carpentry

Addenda – TBD

Substitutions – All Substitutions must be pre-approved to be included in your bid.

Prequalification in Subcontractor Management System (SMS) located at http://sms.jedunn.com

This is a tax-exempt Project.

Bid Bonds – Not required at this time

Insurance – JE Dunn will be providing GL for onsite workers per the included insurance plan. Please review prior to bidding.

Safety – JE Dunn’s Safety Manual has been included in the Front End for review.

MBE/WBE GOALS:

USD 500 and JE Dunn are committed to 100% small business inclusion on the KCKPS School Bond construction work and encourages all small and local businesses to bid, despite there being no stated small business utilization targets attached to this project. Our regularly scheduled outreach and informational events create transparency and are essential to communicating with the small business community. Low, most responsive bidders.

Scopes of Work

• 01A - Final Cleaning

• 02A - Structure Demolition

• 03A - Concrete (Building and Site)

• 03L - Precast Concrete

• 04A - Masonry

• 05A - Structural and Miscellaneous Steel

• 06A - Carpentry & Specialties

• 06E - Finish Carpentry and Casework

• 07A - Waterproofing, Air Barriers and Joint Sealants

• 07B - Roofing and Sheet Metal

• 07C - Firestopping

• 08A - Aluminum Storefronts and Glazing

• 08B - Overhead Coiling Doors

• 08C - Doors, Frames, and Hardware

• 09A - Metal Framing and Gypsum Board

• 09B - Acoustical Ceilings

• 09C - Wood Flooring

• 09D - Resilient and Carpet Flooring

• 09E - Resinous Flooring

• 09F - Wall Coverings, Painting and Finishes

• 09G - Tiling

• 10A - Signage

• 11A - Food Service Equipment

• 11C - Gym Equipment

• 12C - Roller Window Shades

• 14A - Conveying Systems

• 21A - Fire Suppression Systems

• 22A - Plumbing Systems

• 23A – Heating, Ventilating, and Air Conditioning

• 26A - Electrical

• 27A - Communications

• 31A - Earthwork

• 32A - Asphalt Paving

• 32B – Chain Link Fences and Gates

• 32C - Landscaping and Irrigation

• 33A - Site Utilities

Project Schedule:

• Phase 1 - Start June 2019

• Phase 1 - Finish Building May 2020

• Phase 2 - Demo William Allen White July 2020

• Phase 2 - Finish Sitework/Occupancy work by End of August 2020

• TCO issued June 2020