BID PACKAGE 6A - BID FORTHCOMING

GENERAL OVERVIEW:

The Bid Package includes Administration Office and Science Classroom Renovation at FL Schlagle High School.

BIDDING DOCUMENTS:

• Drawings (1 set)

• Specifications (2 volumes)

• Hard copy printing is responsibility of bidder.

• Documents are available through our online plan room, Smart Bid Net.

INSTRUCTIONS TO BIDDERS:

Bid Date – Thursday, November 8, 2018 at 2:00 P.M.

Bid Proposal Form – Section 00 41 23 (include signed scope of work with bid form)

Bid Delivery – Please direct all bids to Jeff Yartz

Must be in sealed envelope; Can be emailed with the exception of the following scopes:

• Masonry

• Carpentry

Addenda - Anticipate one addenda to be issued, addressing bidder questions.

Substitutions – All Substitutions must be pre-approved to be included in your bid.

Prequalification in Subcontractor Management System (SMS) located at http://sms.jedunn.com

This is a tax-exempt Project.

Bid Bonds – Not required at this time

Insurance – JE Dunn will be providing GL for onsite workers per the included insurance plan. Please review prior to bidding.

Safety – JE Dunn’s Safety Manual has been included in the Front End for review.

SMALL BUSINESS INCLUSION:

USD 500 and JE Dunn are committed to 100% small business inclusion on the KCKPS School Bond construction work and encourages all small and local businesses to bid, despite there being no stated small business utilization targets attached to this project. Our regularly scheduled outreach and informational events create transparency and are essential to communicating with the small business community. Low, most responsive bidders.

SCOPES OF WORK

02B – Selective Demolition

04A - Masonry

06F - Carpentry

07I - Joint Sealants and Firestopping

08A - Doors, Frames, and Hardware PM

08C - Aluminum Storefront, Glass, and Glazing

09A - Metal Framing and Drywall

09B - Painting

09C - Tile

09H - Resilient Flooring and Carpet

09E - Resinous Flooring

09F – Acoustical Ceilings

12C – Blinds and Shades

21A - Fire Protection

22A - Plumbing

23A - HVAC

26A - Electrical

27A - Telecommunications

PROJECT SCHEDULE:

Project Schedule will be issued via Addendum:

• Project Start Date 6/3/19

• Project Finish Date 7/31/19

BUILDING AVAILABILITY FOR WALK THROUGHS:

Immediately following the Pre-Bid Meeting October 31, 2018:

• 2:00 – FL Schlagle High School

Open Walk Through