BID PACKAGE 09 BID FINAL FALL 2017

General Overview: 

The Bid Package includes construction of a new 128,000 SF middle school at the existing site of Coronado Middle School.

Bidding Documents:

  • Drawings
  • Specifications
  • Hard copy printing is responsibility of bidder
  • Electronic documents available through Smart Bid Net to invited bidders                 

Instructions to Bidders:

Out to Bid - October 30, 2017

Pre-Bid Date - November 15, 2017

Bid Date - November 30, 2017

Bid Proposal Form – Section 00 41 23 (include signed scope of work with bid form)

Bid Delivery – Please direct all bids to JE Dunn Construction (Jeremy Catlett) 

Must be in sealed envelope; Can be emailed with the exception of the following scopes:

  • Concrete
  • Precast
  • Masonry
  • Carpentry

Addenda – TBD

Substitutions – All Substitutions must be pre-approved to be included in your bid.

Prequalification in Subcontractor Management System (SMS) located at http://sms.jedunn.com

This is a tax-exempt Project.

Bid Bonds – Not required at this time

Insurance – JE Dunn will be providing GL for onsite workers per the included insurance plan. Please review prior to bidding.

Safety – JE Dunn’s Safety Manual has been included in the Front End for review.

MBE/WBE GOALS:

USD 500 is in the process of setting participation targets for the bond projects. It is requested that Bidders actively solicit minority contractors, suppliers and their organization.

Scopes of Work

  • 01A - Final Cleaning
  • 02A - Structure Demolition
  • 03A - Concrete (Building and Site)
  • 03B - Precast Structural Concrete
  • 03C - Precast Architectural Concrete
  • 03D - Decorative Polished Concrete
  • 04A - Masonry 
  • 05A - Structural and Miscellaneous Steel 
  • 06A - Carpentry & Specialties
  • 07A - Waterproofing, Air Barriers and Joint Sealants 
  • 07B - Roofing and Sheet Metal
  • 07C - Firestopping
  • 08A - Aluminum Storefronts and Glazing
  • 08B - Overhead Coiling Doors
  • 08C - Doors, Frames, and Hardware  
  • 09A - Metal Framing and Gypsum Board 
  • 09B - Acoustical Ceilings 
  • 09C - Wood Flooring
  • 09D - Resilient and Carpet Flooring  
  • 09E - Resinous Flooring
  • 09F - Wall Coverings, Painting and Finishes
  • 09G - Tiling
  • 10A - Signage  
  • 11A - Food Service Equipment 
  • 11B - Theatrical Lighting and Equipment
  • 11C - Gym Equipment 
  • 12A - Finish Carpetnry and Casework
  • 12B - Telescoping Stands
  • 12C - Roller Window Shades
  • 12D - Fixed Audience Seating
  • 14A - Conveying Systems
  • 21A - Fire Suppression Systems
  • 22A - Plumbing Systems
  • 23A – Heating, Ventilating, and Air Conditioning
  • 26A - Electrical  
  • 27A - Communications
  • 31A - Earthwork 
  • 31B - Rammed Vibro/Stone Aggregate Piers
  • 32A - Asphalt Paving
  • 32B – Chain Link Fences and Gates
  • 32C - Landscaping and Irrigation
  • 33A - Site Utilities

Project Schedule: 

Project Schedule 

  • Start February 2018
  • Finish Building May 2019
  • Start Building Demo/Site work by end of school year May, 2019
  • Finish Sitework/Occupancy work by end of July 2019
  • TCO issued first week of August 2019 for Fall 2019 classes