BID PACKAGE 8 BID FORTHCOMING FALL 2017

General Overview: 

The Bid Package includes construction of a new 70,000 SF elementary school at the existing site of Welborn Elementary.

Bidding Documents:

  • Drawings
  • Specifications
  • Hard copy printing is responsibility of bidder
  • Electronic documents available through Smart Bid Net to invited bidders                             

Instructions to Bidders:

Out to Bid - September 18, 2017

Bid Date – October 24, 2017

Bid Proposal Form – Section 00 41 23 (include signed scope of work with bid form)

Bid Delivery – Please direct all bids to JE Dunn Construction (PM TBD) 

Must be in sealed envelope; Can be emailed with the exception of the following scopes:

  • TBD

Addenda – TBD

Substitutions – All Substitutions must be pre-approved to be included in your bid.

Prequalification in Subcontractor Management System (SMS) located at http://sms.jedunn.com

This is a tax-exempt Project.

Bid Bonds – Not required at this time

Insurance – JE Dunn will be providing GL for onsite workers per the included insurance plan. Please review prior to bidding.

Safety – JE Dunn’s Safety Manual has been included in the Front End for review.

 

Scopes of Work

  • 02A - Building and Site Demolition
  • 03A - Concrete
  • 03B - Precast Concrete Panels
  • 04A - Masonry 
  • 05A - Steel 
  • 06A - Rough Carpentry
  • 06B - Finish Carpentry, Casework and Specialties
  • 07A - Membrane Roofing 
  • 07B - Sheet Metal 
  • 07C - Joint Sealants, Waterproofing, and Firestopping  
  • 08A - Doors, Frames, and Hardware PM 
  • 08B - Overhead and Coiling Counter Doors 
  • 08C - Aluminum Framing, Glass, and Glazing  
  • 09A - Metal Framing and Gypsum 
  • 09B - Acoustical Ceilings 
  • 09C - Painting 
  • 09D - Carpet and Resilient Flooring and Tiling 
  • 09E - Resinous Flooring  
  • 10A - Signage  
  • 11A - Food Service Equipment 
  • 11B - Gymnasium Equipment 
  • 12A - Window Coverings 
  • 14A - Elevators 
  • 21A - Fire Suppression 
  • 22A - Plumbing 
  • 23A - HVAC 
  • 26A - Electrical  
  • 27A - Telecommunications 
  • 31A - Earthwork 
  • 33A - Site Utilities
  • 32B - Site Concrete 
  • 32A - Asphalt Paving and Markings
  • 32D - Landscaping
  • 32C - Fencing

Project Schedule: 

Project Schedule 

  • Start March 2018
  • Finish Biulding April 2019
  • Start Building Demo/Site work by end of school year May, 2019
  • Finish Sitework/Occupancy work by end of July 2019
  • TCO issued first week of August 2019 for Fall 2019 classes