WHAT'S HAPPENING AT wyandotte

  • As part of deferred maintenance, Wyandotte High received upgrades to the building envelope, fire alarm and roof in the Summer of 2017.

  • Wyandotte High will get all new plumbing. The site utilities and interior plumbing began in January of 2018 and were complete by September 2018.

  • Wyandotte High also received multiple academy space renovations, and security upgrades as part of the bond projects.

  • The following is the completion date of renovations:

    • All Academies - July 2018

    • Secure Entry - July 2018

    • Restrooms - September 2018

  • Please check back for important information regarding updates to your child's school.

  • More information will be available as the bond projects move forward.

Watch this space for monthly progress reports once our upgrade work commences.

Wyandotte Map

 
 

For more information on specific school information, visit Wyandotte's website.